Project: MTR SCL 1107, DIMOND HILL TO KAI TAK TUNNEL, Chun Wo~Seli JV: This project consist of 2 x 7.4M dia EPB TBM Bored tunnel 800m long. The first Tunnel started on 5 Sep 14 and Breakthrough was made on 18 Mar 15